|
Sometimes it’s instructive to follow a specific funding request through the
labyrinth of the SLD review and funding process. As the first in what we expect
will be a series of stories, we offer the “Case of the Unending FRN.”
Chapter 1 – Application: In FY 2001, a school district filed a Form 471
containing two funding requests for Internet service, one for the basic access
service and a smaller one for the maintenance charge on the ISP’s router. The
district assumed the router should be considered an integral part of the
Internet service but, because of the varying treatment of Internet routers over
the years under the SLD rules for Priority 1 on-premise equipment, the
maintenance charge was filed for separately.
| Lesson 1: As a general rule, if an applicant is not sure whether a specific
component of a service is eligible, or whether that component can be included
in a certain funding category, the best approach is to request funding for each
portion of the service in a separate FRN. This is particularly true if the
questionable portion represents 30% or more of the total service cost. If the
SLD finds an error of more than 30% in an applicant’s request, it will deny or
reclassify the entire FRN. Separating a request into two or more component
parts, therefore, can isolate the risk of a 30% or greater filing error on the
questionable portion. |
Chapter 2 – Decision and Appeal: The district received a funding decision on its
application in the first wave of 2001 funding. Its FCDL was dated July 23,
2001. The FCDL approved all FRNs “as submitted” except the router FRN. The SLD
had shifted the service category on this FRN from Internet Access to Internal
Connections and, because the district had only a 40% discount rate, the FRN was
not funded. On August 15, 2001, the district filed an appeal with the SLD.
| Lesson 2: If an applicant believes that the SLD has made a mistake in
processing its application – in this case, the inappropriate service category
reclassification of the router FRN – the only effective remedy is to file an
appeal. |
Chapter 3 – Appeal Decision: On November 6, 2002, the SLD issued an
Administrator’s Decision on Appeal that approved the district’s appeal in full.
Three months later on February 7, 2003, a revised FCDL was sent to the
district. The deadline for submitting an invoice on this FRN was extended until
July 9, 2003.
| Lesson 3: This appeal, which was not particularly complex, nor for a large
amount of money, took 14 months to decide. The SLD’s target for deciding
appeals is shorter, but the appeal process is never likely to be a speedy one.
The three month wait for a formally revised FCDL, which was needed before a
BEAR could be filed on the newly approved funding, was relatively prompt in
this case. (In other cases, such as those requiring a complete application
review, the delay may be substantial.) The invoice deadline extension (to 120
days after the revised FCDL date) was automatic. |
Chapter 4 – Form 486 and BEAR: On February 25, 2003, the district filed a Form
486 for the FRN based on the newly revised FCDL. Shortly thereafter, the
district filed a BEAR seeking reimbursement for the discounted portion of the
router maintenance.
| Lesson 4: Since the FRN had initially been denied funding, the FRN was not
included on the Form 486 that the district filed back in 2001. To activate
funding on the newly approved FRN, a separate Form 486 had to be filed. The
Form 486 must be filed within 120 days to the revised FCDL date. |
Chapter 5 – “Late” Form 486 Decision: Although the district submitted its Form
486 less than three weeks after receiving the revised FCDL, the SLD sent the
district a Form 486 Notification Letter on March 19, 2003, indicating that the
Form 486 deadline had been missed and that the Service Start Date for the FRN
had been reset to February 25, 2003. On April 4, the SLD advised the district
that it would reject the BEAR form. The SLD noted that, while the invoice
deadline had been extended, the new service start date was well after the
allowable FY 2001 service period. A formal notification that the BEAR was not
approved was not issued until June 13, 2003.
Upon investigation, it was found that the SLD had a database problem. The Form
486 deadline for the newly approved FRN was being incorrectly calculated based
on the original FCDL issued in 2001, not on the revised FCDL issued in 2003.
| Lesson 5: Anyone can make a mistake. |
Chapter 6 – Form 486 Appeal: Hoping that the SLD would correct its own problem,
the district waited a month. It then filed an appeal contesting the Form 486
service start date change. The SLD rendered an appeal decision on June 30,
2003, again approving the appeal in full and indicating that a revised FCDL
would be forthcoming.
Based on an exchange of e-mails with the SLD, it was subsequently determined
that a revised FCDL was not needed because the previously revised FCDL was
still correct and valid. But what was needed was a revised Form 486
Notification Letter with a corrected Service Start Date.
| Lesson 6: Even if the SLD admits a mistake, the applicant’s only recourse is to
appeal. Appeals are due within 60 days of the original decision, so all SLD
correspondence must be read promptly and thoroughly. In this case, the appeal
had to be filed within 60 days of March 19, the date of the incorrect Form 486
Notification Letter. If the problem had not been discovered until the BEAR was
formally rejected in June, it would have been too late to try and correct the
error. |
Chapter 7 – To Be Continued: As of this date, the district has yet to receive a
revised Form 486 Notification Letter. Meanwhile, the invoice deadline, which
had been extended only through July 9, has expired. Hopefully a revised Form
486 Notification Letter will be issued shortly. Hopefully, the BEAR deadline
will be automatically extended without the district having to file an invoice
extension request. Hopefully, the BEAR can then be resubmitted and be
successfully processed without further complications. And hopefully, the
district will actually received reimbursement for this FY 2001 award sometime
in early 2004 for the entire amount of – drum roll please – $387.98!
|
Lesson 7: You have to be a little pigheaded to work so hard for so little
money. The good news, however, even if this story is not yet over, is that the
SLD’s procedures for appeal, review, and applicant notification can be made to
work. All it takes is some perseverance. |
|